Bogong Power Station - Construction

AGL Southern Hydro has constructed the Bogong Power Development, part of the Kiewa Hydro Electric Scheme near Mt Beauty in Victoria.
Two turbines will be installed and will generate 140mw. 
Xypex Admix C-1000 NF was specified in 12,000 cubic metres of concrete for the purpose of water proofing and providing long term durability to the structure. Concrete was supplied by Cemex from a mobile batch plant, 32 MPA concrete was dosed at 1%. (In excess of 45,000 kg's of Xypex Admix was used).
Tie bolt holes were patched utilizing the Xypex repair system which included M P&P and Flupps 22ST to 5,000 tie bolts.

Xypex Product(s) Used
  • Error: Missing Layout 'projects' for type prodsimple.